Timeline
The Berri Hospital Redevelopment is expected to be complete by December 2013.
Key milestones for the project include:
- Concept plan released – December 2010
- Managing Contractor appointed - January 2011
- Construction commenced - June 2011
- Works in Stage 1 – July 2011 to February 2013
- New Theatre Building
- New Emergency Department Building
- New Clinical Sterile Supply Department (CSSD)
- New Mental Health Wards
- New Rehabilitation Building
- New Patient Wards
- New Renal Unit
- Works in Stage 2 – February 2013 to December 2013
- New Chemotherapy Unit
- Refurbishment of existing Emergency Department footprint
- Refurbishment of existing Wards
- Construction completed - December 2013