Timeline :: SA Health

Timeline

The Berri Hospital Redevelopment is expected to be complete by December 2013.

Key milestones for the project include:

  • Concept plan released – December 2010
  • Managing Contractor appointed - January 2011
  • Construction commenced - June 2011
  • Works in Stage 1 – July 2011 to February 2013
  • New Theatre Building
  • New Emergency Department Building
  • New Clinical Sterile Supply Department (CSSD)
  • New Mental Health Wards
  • New Rehabilitation Building
  • New Patient Wards
  • New Renal Unit
  • Works in Stage 2 – February 2013 to December 2013
  • New Chemotherapy Unit
  • Refurbishment of existing Emergency Department footprint
  • Refurbishment of existing Wards
  • Construction completed - December 2013